Tuesday, 3 November 2009

In Blue


Looks a bit like the start of a swimming pool.. all the 1200 guage DPM has been laid on top of the stone. The stone was well compacted and a blinding of sand was put on top, all joints in the sheeting were sealed with a double sided tape made specially for the job, it is all pretty standard stuff for building regs. Building inspector has been and passed it ready for the cement slab to be put in tomorrow. This will be 100mm across the whole building. We then have 70mm Celotex insulation on top of which the Under Floor Heating will be installed, and 70mm screed to finish to floor level, but these will be put in after the timber frame has been erected, which is not long now...

No comments:

Post a Comment