MVHR Ducting Installation




Hello again! Sorry there hasn't been any updates recently but the snow has stopped work for the past 3 weeks - we have done some work inside when we have been able to get to site. All the supply run ductwork has been installed - all the bedrooms and the computer room get a supply feed from the MVHR unit. Just the extract run to do, which is a lot easier as we only need to extract from the 2 bathrooms and the kitchen.

The Rockwool Flexi Slab has all been installed, it took 54 Packs to do all of the external walls of the house. We are 'topping up' this insulation upstairs with some loft roll - you can see it in the ductwork photos.

The snow has gone now and we are hoping to get things moving again on site - We need to have completed all the brickwork by 15th Feb so that the windows can be fitted. The roofer is planning to come to site this week - we really need to get the roof on ASAP.