Hello again! Sorry there hasn't been any updates recently but the snow has stopped work for the past 3 weeks - we have done some work inside when we have been able to get to site. All the supply run ductwork has been installed - all the bedrooms and the computer room get a supply feed from the MVHR unit. Just the extract run to do, which is a lot easier as we only need to extract from the 2 bathrooms and the kitchen.
The snow has gone now and we are hoping to get things moving again on site - We need to have completed all the brickwork by 15th Feb so that the windows can be fitted. The roofer is planning to come to site this week - we really need to get the roof on ASAP.